News from the Nasukarasuyama Solar
-
Sep 9th, 2022Environmental study session for Otawara High School
-
Jan 31st, 2020Support offered for recovery from the impact of Typhoon Hagibis (“No. 19”)
-
Jul 31st, 2019A ceremony was held on July 4 to celebrate the completion of Nasukarasuyama Solar power plant.
-
May 31st, 2019Operation commenced on May 1!
-
Mar 31st, 2019Preparations are underway to enable the extra-high-voltage substation to receive power from the plant.
-
Feb 28th, 2019Installation of solar panels has progressed to 80% of completion.
-
Jan 31st, 2019Extra-high-voltage substation equipment has been delivered.
-
Dec 31st, 2018Construction of the retention basins is progressing as scheduled.
-
Nov 30th, 2018Installation of solar panels is progressing.
-
Oct 31st, 2018Driving of piles has begun.