News from the Karumai West Solar
-
Jul 15th, 2021Environmental study session for Karumai High School
-
Nov 18th, 2020Karumai Junior High Schools announce the results of the environmental study session
-
Aug 3rd, 2020An environmental study meeting held at Millet Park Solar House in Karumai town!
-
Jun 30th, 2020The guide map signboard installed at Karumai West Solar Power Plant.
-
Sep 30th, 2019This short five-minute movie presents details of the development and construction process.
-
Aug 31st, 2019A ceremony was held on August 23 to celebrate completion of the construction.
-
Jul 31st, 2019Operation commenced as of July 1.
-
Apr 30th, 2019Power transmission pylons have now been connected to the substation.
-
Mar 31st, 2019The transmission tower has been installed for grid connection
-
Feb 28th, 2019A series of tests are conducted for the electrical equipment