Feb 28th, 2019Concrete pouring work is underway amidst cold conditions.
-
Jan 31st, 2019Rainwater wastewater work is progressing.
-
Dec 31st, 2018Even in the snow, the construction of the retention basins is progressing steadily.
-
Nov 30th, 2018Landscaping of the retention basins is progressing as scheduled.
-
Oct 31st, 2018Construction work commenced in May 2018. Landscaping of the retention basins is currently underway.
-
May 31st, 2018Groundbreaking Ceremony
-
Mar 31st, 2018Finance Close